Cathodic protection systems must be inspected by a certified cathodic protection tester within how many months of installation?

  1. 3 months

  2. 6 months

  3. 12 months

  4. 1 month

The correct answer is: 6 months

The correct answer is based on the regulations that govern cathodic protection systems, which are crucial for preventing corrosion on underground storage tanks (USTs) during their operational life. According to these regulations, a certified cathodic protection tester must inspect these systems within six months of their installation. This requirement ensures that any potential issues with the cathodic protection system are identified and addressed early on, maximizing the effectiveness of the system right from the start. This timely inspection plays a vital role in maintaining the integrity of the USTs and in protecting the environment, as failing to correctly install or maintain these systems can lead to leaks and contamination. The other options reflect different timeframes which do not align with the specific regulatory standards set forth for inspecting installed cathodic protection systems. Hence, selecting the correct timeframe is essential for compliance and serves to uphold safety standards in the industry.